An artist impression of the new underground Wellington Street Bus Station showing the dynamic gate a
 

The second stage of the Perth City Link project, building a new underground bus station, is scheduled for completion in 2016. The bus project is the final transport component of the Perth City Link project.

The scope of work includes:
 

  • Demolition of Platform 11. This will create an above-ground space for City Square, which will be developed by the Metropolitan Redevelopment Authority. 
  • Construction of two temporary bus stations, one on Roe Street (this will be responsible for 75 per cent of services from Wellington Street Bus Station); and the other on Wellington Street.
  • Construction of a new underground, dynamic stand bus station.
  • Demolition and removal of the temporary bus stations.