May 2018 update
News Articles | 11 May 2018

May 2018 update

In one of the project's biggest milestones to date, TBM Grace broke through into the underground station box at Airport Central Station on the evening of Tuesday May 8, 2018.

April 2018 update
News Articles | 19 April 2018

April 2018 update

TBM Grace resumed tunnelling this month and has now successfully installed 1034 rings. The restart follows the completion of a comprehensive review into tunnelling operations.

March 2018 update
News Articles | 13 March 2018

March 2018 update

As we progress towards first trains using the Forrestfield Line in 2020, key infrastructure along the new alignment, including all three new stations, is now well into construction.

February 2018 update
News Articles | 12 February 2018

February 2018 update

We have hit the ground running this year with tunnelling progressing well and construction underway at the stations, cross-passages and emergency egress shafts.

2017 end of year update
News Articles | 3 January 2018

2017 end of year update

Our tunnel boring machines are sprinting towards the end of the year with Grace having tunnelled more than 1300m and Sandy more than 500m.

November 2017 update
News Articles | 9 November 2017

November 2017 update

A lot can happen in a year, and that's certainly been the case since construction of the Forrestfield-Airport Link kicked off on November 3, 2016.

October 2017 update
News Articles | 11 October 2017

October 2017 update

With TBM Grace's journey well underway, and TBM Sandy set to start tunnelling later this month, activity across all sites is ramping up.

September 2017
News Articles | 7 September 2017

September 2017

With TBM Grace now tunnelling and Sandy soon to launch, production of tunnel segments has ramped up over the past month.

August 2017 update
News Articles | 10 August 2017

August 2017 update

In the project's biggest milestone to date, the first of two tunnel boring machines has now begun its 8km underground journey from Forrestfield to Bayswater.

July 2017 update
News Articles | 7 July 2017

July 2017 update

With the first tunnel boring machine launching soon, the project has kicked into full swing.

RSS
123468910Last


Media enquiries about the Forrestfield-Airport Link can be directed to the Public Transport Authority:
Media line: (08) 9326 2526
Email: media@pta.wa.gov.au
Please note emails are monitored Monday to Friday, 9am to 5pm AWST.

Media enquiries from students must be sent from school or university email accounts.