July 2019 update
News Articles | 11 July 2019

July 2019 update

This week the team celebrated our second 130m-long tunnel boring machine (TBM) arriving at Redcliffe Station. TBM Sandy broke through into the underground station box at 9:30am on Saturday, July 6.

Skybridge construction takes to the skies in latest milestone
Media Statements | 2 July 2019

Skybridge construction takes to the skies in latest milestone

Premier Mark McGowan and Transport Minister Rita Saffioti today visisted the developing Skybridge at Airport Central Station 

June 2019 update
News Articles | 7 June 2019

June 2019 update

Tunnel boring machine (TBM) Grace arrived at Redcliffe Station last month, breaking through the one-metre-thick eastern station box wall to a cheering crowd of excited team members.

Forrestfield-Airport Link tunnelling pauses following slurry spill
Media Statements | 14 May 2019

Forrestfield-Airport Link tunnelling pauses following slurry spill

Tunnelling operations have paused on the Forrestfield-Airport Link after a section of piping servicing one of the tunnel boring machines (TBM) dislodged in Tunnel Two, causing a slurry spill.

Record METRONET budget as TBM Grace reaches Redcliffe Station
Media Statements | 13 May 2019

Record METRONET budget as TBM Grace reaches Redcliffe Station

Premier Mark McGowan and Transport Minister Rita Saffioti today welcomed the arrival of TBM Grace to the Redcliffe Station construction site, as the State Government highlighted the significant investment in METRONET as part of this week's State Budget.

May 2019 update
News Articles | 2 May 2019

May 2019 update

Tunnel boring machine (TBM) Grace and her crew reached another milestone earlier this week: completing 4.5km of tunnelling!

Cross Passages and Emergency Egress Shafts Fact Sheet
Fact Sheets | 30 April 2019

Cross Passages and Emergency Egress Shafts Fact Sheet

Given the length of the tunnels, additional infrastructure is required to provide safe egress between the two tunnels and to ground level in the event of an emergency.

April 2019 update
News Articles | 5 April 2019

April 2019 update

A major milestone was celebrated this week with all tunnel segments required for the 8km twin-bored tunnels produced.

March 2019 update
News Articles | 11 March 2019

March 2019 update

Concrete has been the big ticket item in the past month with slab pours taking place left, right and centre. A lot of construction work has become more visible now with above-ground structures starting to take shape across several of the sites.

Tunnel Boring Machines fact sheet
Fact Sheets | 6 March 2019

Tunnel Boring Machines fact sheet

Tunnel boring machines (TBMs) are large machines that excavate below the ground surface, while simultaneously installing concrete lining units to build a tunnel.

RSS
123456789


Media enquiries about the Forrestfield-Airport Link can be directed to the Public Transport Authority:
Media line: (08) 9326 2526
Email: media@pta.wa.gov.au
Please note emails are monitored Monday to Friday, 9am to 5pm AWST.

Media enquiries from students must be sent from school or university email accounts.