High Wycombe Station fact sheet
Fact Sheets | 12 October 2020

High Wycombe Station fact sheet

Located adjacent to Dundas Road, east of the Forrestfield freight marshalling yard and south of Maida Vale Road, High Wycombe Station will provide an accessible and efficient transport option to and from the city for Perth’s eastern suburbs and foothills.

October 2020 update
News Articles | 8 October 2020

October 2020 update

Track laying within Tunnel Two (TBM Sandy's tunnel) is advancing on a daily basis, with more than 40 per cent of skeleton track (rail strings clipped to sleepers) in place, and almost 30 per cent of slab track (skeleton track embedded in concrete) complete.

Youth-led art piece to transform High Wycombe Station entry
Media Statements | 7 October 2020

Youth-led art piece to transform High Wycombe Station entry

Young people from the Kalamunda area will have the chance to brainstorm, design and install a large new outdoor mural as part of the Forrestfield-Airport Link project.

September 2020 update
News Articles | 11 September 2020

September 2020 update

Progress in the Airport Line's twin-bored tunnels has really gained momentum, with 90 per cent of the tunnel invert slab now poured and cured.

Building for Tomorrow program a key feature of economic recovery
News Articles | 23 August 2020

Building for Tomorrow program a key feature of economic recovery

The McGowan Government is building Western Australia's economy back-up from the pandemic by embarking on Building for Tomorrow, the biggest transport infrastructure program WA has seen.

Claremont METRONET tracklaying contract awarded
Media Statements | 17 August 2020

Claremont METRONET tracklaying contract awarded

Turnback will allow high frequency services on Fremantle and Airport lines

August 2020 update
News Articles | 10 August 2020

August 2020 update

The first kilometre of track has been laid between Redcliffe and Airport Central stations.

Tunnel fit-out and track laying fact sheet
Fact Sheets | 10 August 2020

Tunnel fit-out and track laying fact sheet

Tunnel fit-out is an essential part of the project and includes installation of rail infrastructure and electrical, mechanical, hydraulic, safety and communications systems.

Tracklaying underway on METRONET’s Airport Line
Media Statements | 30 July 2020

Tracklaying underway on METRONET’s Airport Line

The transformational METRONET Forrestfield-Airport Link project has reached another major milestone, with tracklaying in the eight-kilometre tunnels now underway.

July 2020 update
News Articles | 3 July 2020

July 2020 update

Earlier this year we asked residents and businesses within the City of Kalamunda to choose their preferred name for the new line's terminus station.

RSS
245678910Last


Media enquiries about the Forrestfield-Airport Link can be directed to the Public Transport Authority:
Media line: (08) 9326 2526
Email: media@pta.wa.gov.au
Please note emails are monitored Monday to Friday, 9am to 5pm AWST.

Media enquiries from students must be sent from school or university email accounts.