November has seen a high volume of concrete works taking place across our construction sites.
TBM Grace has made good progress in the last month and has now tunnelled 44 per cent of the entire tunnel length between Forrestfield and Bayswater Junction.
At 1pm on Saturday September 22 a leak developed in a cross passage between the two Forrestfield-Airport Link tunnels, causing a sinkhole to form at the surface.
Earlier this month both tunnel boring machines (TBMs) reached another milestone, having now built a third of the entire length of the tunnels between Forrestfield and Bayswater Junction.
The McGowan Government will provide a multi-deck car park at the future Forrestfield Station to open up space for a future METRONET precinct.