| Transperth
                  Bus Operations 
 Transperth bus operations succeeded in minimising
                    the impact of construction works associated with the
                    Southern Suburbs Railway on bus punctuality through
                    improved traffic management schemes and timetable
                    adjustments. As a result of these measures the actual
                  result for 2004/05 was better than the target. 
                    Transperth Ferry Operations   
 Transperth ferry operations has maintained its
                consistent high level of performance. | Country passenger rail and road coach services    Transwa Rail   Prospector services      
 During commissioning of the new Prospector railcars,
                      reliability problems were experienced. There was also
                      a significant increase in freight traffic which requires
                      more train crossings, thus increasing travel time.                       Australind 
 The target for 2004/05 could not be achieved due to
                  severe speed restriction following the track upgrade
                  work from Pinjarra to Mundijong.                   AvonLink 
 The data for 2004/05 includes the newly introduced
                  Merredin service where on-time running has been
                  affected by freight train traffic. |